Second Northern Greater Mekong Subregion Transport Network Improvement Project - Additional Financing

Details

Project 41444-013
Related Projects Search
Type Loan
Sector Transport
Country Viet Nam
Start 2015
End 2021
Status Ongoing
Last Edited 05 Jul 2021

Funding

US$('000) 77,850

Project Description

The GMS Northeastern Corridor (encompassing Nanning in Guangxi Province, People's Republic of China; Hanoi and Thanh Hoa in Viet Nam; Louang Phrabang, Lao Peoples Democratic Republic; and Bangkok, Thailand) is one of the corridors identified in the GMS Transport Sector Strategy Study and links northeastern Lao PDR and northern Viet Nam. Many of the roads in the transport corridor have been improved including the sections of the corridor in northeastern Lao PDR and northern Viet Nam under the ongoing project (L2703 VIE) to maximize the economic potential of the GMS Northeastern Corridor and to improve northern Lao PDR with year-round access to seaports. As the road conditions between km 59.8 (where Highway 217 intersects with Ho Chi Minh Highway which connects Hanoi and Ho Chi Minh cities) and km 104.9 have significantly deteriorated due to the increased traffic (coming from Na Meo, Hanoi, and Ho Chi Minh cities) and the vehicle overloading, the Government of Viet Nam requested ADB to consider providing additional financing for full scale improvement of the road section km 59.8- 104.9 rather than simple repair as originally planned under L2703.




Progress (as of March 2021)

Ongoing. Started by September 2017. To be completed by 30 June 2020.

Contacts

Contact 1
Contact Name Nguyen, Khoa Dinh
Organization Asian Development Bank
Email knguyen@adb.org
Contact 2
Contact Name -
Organization -
Email -

News and Multimedia

No photos for this project.
Please log in to upload photos for this project.

Add one or more photos to this project


  • Truck traffic across the border increases from 100 trucks per day in 2009 to 220 trucks per day in June 2016
  • Road accidents per vehicle- km on routes 6, 6A, 6B, and 1C in the Lao PDR and Highway 217 in Viet Nam reduced by 15% by June 2016
  • At least 50% of community facilitators in the community- based road safety campaign are women by June 2016
  • At least 50% of paid community facilitators in the community-based road safety campaign are women by December 2018