Road Network Improvement Project (formerly GMS: Deepening Connectivity of Southern Economic Corridor Project)

Details

Project 41123-015
Related Projects Search
Type Loan
Sector Transport
Country Cambodia
Start 2017
End 2023
Status Ongoing
Last Edited 05 Jul 2021

Funding

US$('000) 76,940

Project Description

The originally proposed project name was GMS: Deepening Connectivity of Southern Economic Corridor, later on, it was changed to Second Road Asset Management Project (Second RAMP) and finally, the project title now is Road Network Improvement Project under ADB Loan 3576-CAM (COL). The project will improve about 147 km of flood-prone and unsafe national roads through provision of periodic maintenance and rehabilitation on NR6 (50 km) and NR1 (97 km), respectively, with asphalt-concrete pavement (under a performance-based contract), which are high-priority roads connecting Cambodia with Thailand and Viet Nam.




Progress (as of March 2021)

Ongoing. As of June 2020, asphalt overlay work has been completed with the following cost estimates: NR1: $21,150,004.64 NR6: $10,841,065.62. For CW-4, ADB provided no objec- tion to MPWT-s recommendation to award contact to the first-ranked bidder on 17 February 2020. Contract award is expected in Q1 2020. Project is expected to close in June 2023

Contacts

Contact 1
Contact Name Islam, Mohammad Nazrul
Organization Asian Development Bank
Email mislam@adb.org
Contact 2
Contact Name -
Organization -
Email -

News and Multimedia

No photos for this project.
Please log in to upload photos for this project.

Add one or more photos to this project


  • https://www.adb.org/news/adb-help-enhance-transport-efficiency-management-cambodia